Grattan Square Works - Update!

• Go Dungarvan has selected a contractor (Wills Brothers Limited). The Contractor must supply particular documentation to the Go Dungarvan Team by Friday 16 October
• The Go Dungarvan Team, including their full time engineer assigned to this project, will meet with the Contractor next week where the contractor will outline the programme of work devised
• The letter of acceptance is expected to be sent to the contractor on Thurs 22 October and work must start within 20 days of this
• The contractor must observe the December ban of works on Grattan Square
• The entire contract including the 4 week Christmas Ban is estimated to take 36 weeks and finish end June 2016
• A council engineer will be present on the project for the 36 weeks